Author Topic: Sheringham wind farm  (Read 2434 times)

Offline Robert J Smith

  • Top Poster
  • *****
  • Posts: 5,820
    • View Profile
Sheringham wind farm
« on: August 18, 2011, 04:52:39 PM »
There seems to be a lot of activity around the Sheringham wind farm project off the north Norfolk coast, does anyone know what port these vessels work from?

Regards

Bob

Offline laurie

  • Quite a regular
  • **
  • Posts: 65
    • View Profile
Re: Sheringham wind farm
« Reply #1 on: August 18, 2011, 06:09:19 PM »
Not sure where the installation vessels are working from, but the maintenance base is Wells next the Sea

Laurie

Offline Robert J Smith

  • Top Poster
  • *****
  • Posts: 5,820
    • View Profile
Re: Sheringham wind farm
« Reply #2 on: August 19, 2011, 05:20:19 PM »
Hi Laurie,

Thanks for the info.

Regards

Bob

Offline andrewjam1

  • Newcomer
  • Posts: 1
    • View Profile
Re: Sheringham wind farm
« Reply #3 on: August 19, 2011, 08:43:14 PM »
hi

Most of the crew boats are working out of wells next the sea ,
the Constructor ,Marineco Hathi , Marineco Shamal and Husky are working from Great Yarmouth .
the OLEG STRASHNOV has been piling and installing TPs , she is sailing to Vlissingen to load, she is assisted by tugs Boulder and Typhoon
the jackup rig GMS Endeavour is installing the Turbines she is sailing from Great yarmouth as well

best Regards

Andrew

Offline Robert J Smith

  • Top Poster
  • *****
  • Posts: 5,820
    • View Profile
Re: Sheringham wind farm
« Reply #4 on: August 20, 2011, 02:19:25 PM »
Many thanks Andrew, I thought Great Yarmouth would be involved.