Hi all,
Cropped this photo as much as possible.
These were written on the side of a bunkering tanker alongside but I'm wondering what they mean?
Regards,
-
It simply means each of those lines onboard the ship have been pressure tested to 15 bar and are satisfactory. I can't remember how often these need to be done but 5 years is ringing a bell for some reason.
In case anyone asks, the lines are the pipes product, water, air, hydraulic fluid, etc run through.
Regards Robbie.
-
The tests have to be done from ships side yearly and from classification side at least every 5 years. However
PSC controls can check them anytime and during intermediate surveys too
-
Oil Discharge Monitoring Equipment.....